Saudi Building Code requirements for construction projects
The Saudi building code sets the technical standards that shape safe, durable and properly approved
construction across the Kingdom. It covers structural design, fire protection, electrical work, HVAC,
plumbing, energy performance and other key parts of a building project. For property owners and businesses
in Riyadh, meeting these requirements is essential for permit approval, site inspections and smooth project
handover.
A well-managed project also reduces costly design changes, material mistakes and delays once construction is
already underway. Working with an
experienced construction company gives you better control over
drawings, technical coordination, site execution and final documentation from the start.
The Saudi Building Code 2024 is the current edition and has applied to all building
occupancy types across the Kingdom since June 30, 2025. In this guide, we explain the main Saudi building
code requirements, Balady permit process, construction-stage compliance, occupancy approval and the
responsibilities of each project party.
The Saudi building code sets the minimum technical rules for designing, building, renovating and maintaining
properties across the Kingdom. Its main purpose is to keep construction work safe, consistent and suitable
for Saudi conditions. The code covers villas, offices, factories, warehouses and public buildings, along
with structural, electrical, HVAC, plumbing and fire-protection systems.
Following the right requirements helps protect occupants, reduce property damage and improve how the
building performs after handover. It is different from municipal planning rules, which usually deal with
land use, plot setbacks, building height, parking and site access.
Key Saudi Building Code sections and where they apply
A construction project may need to follow several Saudi building codes, depending on the building type, use
and technical systems involved. The table below shows the main SBC sections and explains where each one
applies during design, construction and building operation.
Code
Main subject
Practical project relevance
SBC 201
General building requirements
Occupancy, building use, accessibility and general safety
SBC 301
Structural loads, seismic and wind
Structural loading and resistance to environmental forces
SBC 302
Construction requirements
Construction-stage controls and site work
SBC 303
Soils and foundations
Soil investigation and foundation design
SBC 304–312
Structural materials and systems
Concrete, masonry, steel, precast and specialised systems
SBC 401
Electrical systems
Electrical loads, wiring, grounding and protection
SBC 501
Mechanical systems
HVAC, ventilation, exhaust and duct systems
SBC 601–602
Energy conservation
Non-residential and residential energy performance
SBC 701–702
Plumbing and sewage
Water supply, drainage, plumbing and private sewage
SBC 801
Fire protection
Fire resistance, alarms, suppression and evacuation
SBC 901
Existing buildings
Alteration, assessment and use of existing structures
SBC 1001
Green buildings
Resource efficiency and sustainable construction
SBC 1101–1102
Residential buildings
Requirements for applicable residential construction
SBC 1201
Fuel gas
Fuel-gas systems and installations
SBC 1401
Pools and spas
Safety and construction of pools and spa facilities
Essential construction requirements under the Saudi Building Code
Saudi construction rules cover more than the main structure. They also guide site planning, fire safety,
electrical work, ventilation, plumbing and energy use. The exact requirements depend on the project type,
location, height and intended activity. A
villa construction in Riyadh will not follow the
same technical path as a factory, hotel or large
warehouse construction.
1. Land, site and municipal requirements
Before design starts, the project team should check the plot documents, land use and cadastral information.
Setbacks, building height, road access and parking may affect the whole layout. These planning rules must
also match the relevant municipality requirements.
Land-use approval
Plot boundaries
Required setbacks
Site access
2. Soil testing and foundation design
The soil condition must be known before choosing a foundation system. A soil report can show bearing
capacity, groundwater level and possible settlement risk. In some Riyadh sites, ground conditions may change
even between nearby plots.
Soil investigation
Groundwater check
Bearing capacity
Foundation type
3. Structural safety requirements
The structural design must account for the building’s weight, use and local environmental conditions.
Engineers calculate dead loads, live loads, wind effects and other forces before preparing the final
drawings. Columns, beams, slabs and foundations should then be built according to those approved details.
Load calculations
Concrete design
Steel reinforcement
Structural inspection
4. Fire and life-safety requirements
Fire safety affects the building layout from the early design stage. Exit routes, fire-rated walls, alarms
and suppression systems must match the building use and number of occupants. A warehouse, restaurant and
office will each need a different fire-safety review.
Emergency exits
Fire alarms
Rated walls
Fire suppression
5. Electrical system requirements
Electrical planning begins with a proper load calculation. The design should cover wiring, distribution
boards, grounding, circuit protection and emergency systems where needed. Wet areas, external equipment and
high-demand machinery need extra care during installation.
Load schedule
Distribution boards
Grounding system
Circuit protection
6. HVAC and ventilation requirements
Cooling and ventilation are major concerns in Saudi buildings because of the long hot season. The system
must provide enough cooling, fresh air and exhaust without wasting energy. Kitchens, toilets, factories and
enclosed service rooms often need separate ventilation arrangements.
Cooling load
Fresh-air supply
Exhaust systems
Duct coordination
7. Plumbing and drainage requirements
Plumbing work includes water supply, sanitary drainage, rainwater discharge and pipe ventilation. The
drawings should match the floor levels, fixture locations and utility connection points. Poor coordination
can lead to wrong slopes, blocked routes or later slab cutting.
Water supply
Drainage slopes
Pipe ventilation
Fixture locations
8. Energy-efficiency requirements
The building envelope and MEP systems should reduce unnecessary energy use. Roof insulation, wall
insulation, glazing and HVAC efficiency all matter in Riyadh’s climate.
Residential building construction and
commercial building construction may follow different
energy-conservation requirements.
Thermal insulation
Efficient glazing
HVAC performance
Lighting controls
9. Accessibility and safe movement
Buildings should allow safe and practical movement for all users. Depending on the project, this may include
accessible entrances, ramps, lifts, toilets and parking spaces. Corridors and doors should also support
normal movement and emergency evacuation.
Accessible entrance
Safe ramps
Clear corridors
Accessible toilets
10. Approved construction materials
Materials should match the approved drawings, specifications and test requirements. Concrete, steel,
insulation, cladding and fire-rated products may need certificates or supplier documents. Changing materials
on site without technical review can affect safety, performance and final approval.
Material certificates
Approved suppliers
Fire-rated products
Controlled substitutions
Documents required before applying for a building permit
A building permit application needs clear land, design and contractor documents before work can move
forward. The exact list may change by municipality, project size, building use and site condition. In
Riyadh, most applications are arranged through the Balady platform with support from approved engineering
offices.
Property ownership document: An updated title deed, housing contract or valid investment contract
is needed to confirm the applicant’s right to develop the land.
Cadastral report: The cadastral report shows the plot boundaries, dimensions, road access and other
site details used in the permit drawings.
Architectural design office contract: An approved architectural office prepares the drawings and
submits the permit application through the required digital system.
Supervising engineering office contract: A supervising office is appointed to follow the approved
drawings and inspect key stages during construction.
Construction contractor details: The permit file normally includes an appointed contractor who will
carry out the work under the approved project scope.
Soil study report: A soil report checks bearing capacity, groundwater and ground conditions before
the foundation design is finalised.
Latent defects insurance: Applicable projects may need latent defects insurance before the final
building permit can be issued.
Additional approvals and fee records: Traffic studies, activity approvals, declarations and payment
receipts may also be required depending on the project.
Saudi building permit process through Balady
The building permit process is completed online through
the Balady platform, but several
parties take part. The owner, design office, technical inspector, municipality, supervisor, contractor and
insurer each handle a separate stage.
Step 1: Authorise a design engineering office
The property owner first appoints and authorises an approved design engineering office. This office opens
the application and manages the main permit documents on Balady.
Step 2: Prepare the drawings and application
The design office selects the cadastral report, fills in the land details and prepares the architectural and
structural drawings. It then uploads the required files, accepts the municipal undertakings and submits the
application.
Step 3: Complete the Saudi building code review
The application is assigned to a technical inspection company through the insurance process. The inspector
checks the drawings against the Saudi building code and returns any comments to the design office.
Step 4: Receive municipal design approval
After the technical review, the application moves to the responsible municipality. Municipal staff may
request changes or issue the design approval certificate when the file is accepted.
Step 5: Appoint the supervising office and contractor
The owner and design office are notified to complete the contracting stage. A supervising engineering office
and building contractor are selected, then each party accepts the appointment.
Step 6: Complete the contractor submission
The contractor reviews the assignment, enters the requested information and attaches the remaining
documents. The completed data is then forwarded to the insurance company through Balady.
Step 7: Issue and pay for latent defects insurance
The insurance company creates the latent defects insurance request and sends a payment link. The policy is
issued after payment, without a separate application for permits submitted after 25 June 2025.
Step 8: Pay the fees and receive the permit
The design office reviews the municipal fees and issues the payment invoice. Once the required fees and
insurance payment are complete, the building permit can be issued.
Saudi Building Code compliance during construction
Code compliance does not end once the permit is issued. The site team must follow the approved drawings,
materials and inspection requirements throughout the build. Small changes on site can create bigger problems
later, especially during testing, final inspection and occupancy approval.
Follow the approved drawings: Construction work should match the approved architectural, structural
and MEP drawings without uncontrolled changes.
Use approved construction materials: Concrete, steel, insulation, cables, pipes and fire-rated
products should match the submitted specifications and certificates.
Maintain proper site supervision: The supervising engineering office should check important stages
before concrete casting, closing walls or covering service lines.
Coordinate structural and MEP work: Ducts, pipes, cable trays and slab openings must be checked
early so they do not cut through beams or important structural areas.
Complete required tests and inspections: Concrete tests, waterproofing checks, plumbing pressure
tests and electrical inspections should be recorded during the work.
Protect fire-rated areas: Openings around pipes, ducts and cables must be sealed correctly where
they pass through fire-rated walls or floors.
Record design changes: Any necessary site change should be reviewed by the responsible engineer and
added to the updated drawings.
Prepare final project documents: Inspection reports, test records, material approvals and as-built
drawings should be ready before handover and occupancy application.
Occupancy certificate requirements after construction
An
occupancy certificate
confirms that the building work has been completed and accepted by the responsible authority. It is
different from the original building permit, which allows construction to begin based on the approved plans.
The application is made after the main construction, testing and required site work are finished.
For a new project, the supervising engineering office completes the building reports, enters the final
details and submits the request through Balady. Approved drawings, inspection records, test reports and
final project documents should be complete, as missing papers or unapproved site changes may hold up the
process.
The occupancy certificate confirms construction completion, while the building-compliance certificate checks
the Ministry’s appearance and urban-compliance criteria and is generated after occupancy approval.
Who is responsible for Saudi Building Code compliance?
Saudi building code compliance is shared between the owner, engineering offices, contractor, suppliers and
testing teams. The table below shows the main role of each party from design and permit approval through
construction, inspection and final testing.
Project party
Main responsibility
Property owner
Appoint qualified parties and authorise the project
Design engineering office
Prepare coordinated, compliant designs
Technical inspection company
Review designs for SBC compliance
Municipality
Review and approve the permit application
Supervising office
Monitor approved construction work
Contractor
Execute the work according to approved documents
Specialist subcontractors
Complete technical systems correctly
Suppliers
Provide compliant materials and documentation
Testing agencies
Perform applicable material and system tests
Why early code coordination reduces construction problems
Saudi building code requirements should be checked while the drawings are still being prepared, not after
work starts on site. Early coordination between architectural, structural and MEP teams helps avoid delays,
rework and costly changes during construction.
Fewer drawing conflicts: Early review helps stop ducts, pipes and cable trays from clashing with
beams, columns or ceiling levels.
More accurate BOQ preparation: Clear and coordinated drawings make material quantities, labour
needs and the
building construction project costs
easier to calculate.
Better permit submissions: Complete technical documents reduce repeated comments from inspectors,
municipalities and other approval parties.
Less site rework: Problems found on drawings cost less to fix than concrete cutting, wall breaking
or service relocation later.
Safer fire protection planning: Exit routes, fire-rated walls, alarms and suppression systems can
be placed correctly before the layout is finalised.
Easier material selection: The team can choose suitable insulation, cables, pipes and fire-rated
products before procurement begins.
Smoother construction scheduling: Structural, MEP and finishing work can follow a practical order
without one trade blocking another on site.
Faster testing and handover: Proper coordination leaves fewer unresolved issues during inspection,
commissioning and occupancy-certificate preparation.
How Concept Excellence supports construction projects in Saudi Arabia
Concept Excellence is a reliable construction management company in Saudi Arabia, working
on residential, commercial and industrial projects. Our team handles planning, technical coordination, site
work and final handover with practical knowledge of Riyadh construction conditions. We also bring experience
in structural work, MEP systems, HVAC, fit-out and day-to-day site control.
Initial construction planning: We review the site, project scope, budget and technical needs before
the main drawings and work schedule are prepared.
Architectural and technical coordination: Our team checks architectural details against structural,
electrical, plumbing and mechanical requirements before site execution.
Construction management: We manage work schedules, contractors, materials and site activities so
each stage follows the agreed project plan.
Structural-work coordination: Foundation, columns, beams, slabs and steel details are coordinated
with the approved structural drawings and site conditions.
MEP and HVAC coordination: We plan electrical, plumbing, drainage, ventilation and cooling routes
to reduce clashes inside walls, slabs and ceilings.
Material planning: Materials are selected and scheduled based on the project specification, site
sequence, availability and expected performance.
Site execution: Our site team follows the approved drawings, daily work programme and technical
instructions during each construction stage.
Quality control: We check workmanship, material use, measurements and key installation details
before the next stage moves forward.
Interior fit-out: Concept Excellence manages partitions, ceilings, flooring, joinery, lighting and
finishing work for completed interior spaces.
Testing and handover support: We coordinate final system checks, snag work, project records and
handover documents before the building is delivered.
Plan your construction project with the right technical support
Concept Excellence supports construction projects in the major cities in Saudi Arabia like Riyadh, Jeddah,
Dammam, etc., with planning, coordination, site management and handover assistance. Our team works across
structural, MEP, HVAC and interior fit-out stages, so the project stays connected from start to finish.
Call us at +966 57 101 4006
today to discuss your construction project
and the support needed for safe, organised site execution.
Saudi construction rules can feel confusing at first, especially when permits, engineering offices and
site inspections are handled separately. These FAQs explain the main points that property owners and
developers in Riyadh often need to understand before starting work.
Is the Saudi Building Code mandatory for construction projects?
Applicable construction work must follow the relevant Saudi building code requirements. The exact
rules are not identical for every project, as building use, height, size, location and technical
systems can change what is required.
What documents are needed for a building permit in Saudi Arabia?
The permit file may include property documents, a cadastral report, engineering-office appointments,
contractor details, a soil report and latent-defects insurance. External approvals may also be
needed, depending on the building activity and project type.
Is a soil study required before construction?
A soil study is normally part of the building-permit requirements listed by Balady. It gives the
structural team site-based information for foundation design, including ground condition, bearing
capacity and possible groundwater concerns.
What fire-safety requirements apply to a Saudi construction project?
Fire requirements depend on the building’s use, occupancy, height and risk level. The project may
need suitable exit routes, fire-rated construction, alarm systems, suppression equipment and Civil
Defense review under SBC 801 and related safety regulations.
What is the difference between a building permit and an occupancy certificate?
A building permit allows approved construction work to move forward. An occupancy certificate is
requested after completion and confirms that the building has been completed through the applicable
authority process, with the supervising engineering office preparing the required report.
ما هو كود البناء السعودي؟
كود البناء السعودي هو مجموعة من المتطلبات الفنية واللوائح والإرشادات المرتبطة بأعمال البناء، ويُطبّق
في مختلف أنحاء المملكة. ويشمل سلامة المباني، والصحة العامة، والأعمال الإنشائية، والأنظمة الرئيسية
داخل المبنى.
هل يمكن تعديل التصميم المعتمد أثناء التنفيذ؟
لا ينبغي للمقاول إجراء أي تعديلات عشوائية على التصميم المعتمد. ويمكن إضافة بعض عناصر المبنى أو
تعديلها أو إزالتها من خلال خدمة التعديل المناسبة في منصة بلدي، مع تحديث المخططات والحصول على مراجعة
الجهة المختصة عند الحاجة.
Planning your construction project?
Concept Excellence provides reliable technical support for smooth project execution.